Uzbekistan
POSCO Road construction project
- 1st site : URGENCH
- Length : 91KM
- Duration : 2009~2012
-
- 2nd site : BUKHARA
- Length : 85KM
- Duration : 2013~2015
- Construction : POSCO E&C
UGCC project
- Site location : SURGIL
- Duration : 2013~2016
- Construction : SEC, HEC, GS Engineering
- Transportation goods : Equipment, Materials, Construction Machinery
Hyundai Construction Equipment
- Commodity : excavator, wheel loader
- Transportation quantity : 256 units
- Destination : Tashkent, Bukhara, Urgenchi
- Duration : 2012 ~
Doosan Infracore
- Commodity : excavator, wheel loader
- Transportation quantity : 217 units
- Destination : Tashkent, Nukhus
- Duration : 2012 ~
Main KANDYM project
- Site location : BUKHARA
- Duration : 2015~2017
- Construction : 현대엔지니어링
- Transportation goods : Equipment, Materials, Construction Machinery
Talimarjan Power Plant project
- Site location : Karshi
- Duration : 2015 ~ Mar. 2017
- Construction : HEC